Which process uses the schedule baseline to assess deviations and forecast completion?

Study for the Landini Certified Associate in Project Management Exam. Prepare with interactive flashcards and in-depth multiple-choice questions. Each question includes hints and answers. Ace your CAPM exam!

Multiple Choice

Which process uses the schedule baseline to assess deviations and forecast completion?

Explanation:
Tracking performance against the approved schedule baseline to identify deviations and forecast finish dates is the work of controlling the schedule. The schedule baseline is the committed version of the project timeline, and controlling the schedule compares actual progress to this baseline, analyzes variances, and uses that information to predict when the project will be completed. This process keeps the schedule realistic by updating it as needed and guiding corrective or preventive actions to stay on track. Other activities focus on planning how to manage the schedule, communicating with stakeholders, or closing the project—areas that set up or wrap up the work rather than continuously measuring performance against the plan.

Tracking performance against the approved schedule baseline to identify deviations and forecast finish dates is the work of controlling the schedule. The schedule baseline is the committed version of the project timeline, and controlling the schedule compares actual progress to this baseline, analyzes variances, and uses that information to predict when the project will be completed. This process keeps the schedule realistic by updating it as needed and guiding corrective or preventive actions to stay on track. Other activities focus on planning how to manage the schedule, communicating with stakeholders, or closing the project—areas that set up or wrap up the work rather than continuously measuring performance against the plan.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy